|
Miracle Faith Dome Recap
1995 land-tracts 16 & 17 purchased
for $80,000.00
tract 17 approx. $40,000
2003 expansion plans begin
2004 Community Council Hearing approval
2005 total cost of project approx.
$2,400,000.00 to complete 1st phase
[includes: dome, air conditioning,
parking lot; underground infrastructure:
(electrical, water & sewer); walkways; landscaping;
elevator, fire hydrants, existing sewer to code;
office trailer to code (accommodation for future
construction); fire sprinklers, etc.]
Refinanced debt / acquired
$1,800,000.00
$600,000 went to service existing mortgage
$1,200,000 went towards current construction
$1,200,000 projected congregational
contributions
Professional services and construction began
Capital stewardship campaign concluded /
pledges begin
2005 - 2008 congregation contribution
$699,562.00
Increasing costs due to hurricanes
& cost of construction
materials*
2006 pledges continued
Shell of dome completed
construction phases continue
2007 pledges continued
Building Better Communities Grant awarded
$605,000.00
Summary
$3,300,000 revised total estimated
cost*
$1,200,000 construction monies from refinance
in 2005
$2,100,000 revised projected congregational
contributions
$ 699,562 congregational
contribution thus far - 2008
$1,400,474 balance to complete
$ 605,000 Building Better
Communities Grant
$ 795,474 needed to complete
Miracle Faith Dome
|