Miracle Faith Dome Recap

1995 land-tracts 16 & 17 purchased for $80,000.00
tract 17 approx. $40,000
2003 expansion plans begin
2004 Community Council Hearing approval
2005 total cost of project approx. $2,400,000.00 to complete 1st phase

[includes: dome, air conditioning, parking lot; underground infrastructure: (electrical, water & sewer); walkways; landscaping; elevator, fire hydrants, existing sewer to code; office trailer to code (accommodation for future construction); fire sprinklers, etc.]

Refinanced debt / acquired $1,800,000.00
$600,000 went to service existing mortgage
$1,200,000 went towards current construction
$1,200,000 projected congregational contributions
Professional services and construction began
Capital stewardship campaign concluded / pledges begin
2005 - 2008 congregation contribution $699,562.00

Increasing costs due to hurricanes & cost of construction
materials*

2006 pledges continued
Shell of dome completed
construction phases continue
2007 pledges continued

Building Better Communities Grant awarded $605,000.00

Summary

$3,300,000 revised total estimated cost*
$1,200,000 construction monies from refinance in 2005
$2,100,000 revised projected congregational contributions
$   699,562 congregational contribution thus far - 2008
$1,400,474 balance to complete
$   605,000 Building Better Communities Grant
$   795,474 needed to complete Miracle Faith Dome

 

  Related Pages

If you are here to get
information on Resources,
then you may also find the
following pages helpful.



Connection Groups

Ministry Home

Discipleship Track


Calendar

click here to get more  Christian Resources
from AG.org
|

Now where did I see that verse?

Click here to search for any verse in the Bible!
 

 
© Copyright 1998-2008 Upper Room Assembly of God